“Nerve Centre” Arrives Offshore Senegal For BP’s LNG Project

“nerve-centre”-arrives-offshore-senegal-for-bp’s-lng-project

© Supplied by BPA platform on a big red ship

QU facilities delivered to the GTA LNG project. Senegal. Supplied by BP Date; 19/08/2022

The quarters and utilities (QU) facility has been delivered to the Greater Tortue Ahmeyim LNG project, offshore Senegal and Mauritania.

BP (LON:BP) vice president Massaer Cisse announced the delivery on LinkedIn.

Red accommodation ship docked at floating facility © Supplied by BP
Picture shows; QU facilities delivered to the GTA LNG project. Senegal. Supplied by BP Date; 19/08/2022

“The QU will be the nerve centre of the hub terminal and provide accommodation for the diverse workforce who will operate it. This is a significant milestone for both the construction of the hub terminal and for the project,” he said.

Chinese manufacturer CIMC Raffles completed construction of the QU facility on May 31. It then travelled 11,885 nautical miles to the Senegal-Mauritania border.

Seaway 7’s heavy lift Seaway Hawk transported the facilities from China. The facilities were towed from CIMC’s yard to Yantai, where it was then floated onto the Seaway Hawk.

BP signed the contract with the Chinese builder in April 2019.

CIMC said the platform was 95 metres long and 70 metres wide, weighing more than 10,000 tonnes. It has more than 540,000 metres of cables and more than 9,000 explosion proof pieces of equipment.

Coloured smoke next to offshore platform © Supplied by CIMC Raffles
Picture shows; Quarters for the GTA LNG project. China. Supplied by CIMC Raffles Date; 31/05/2022

It will host up to 216 staff, in addition to the main control room and the port control room.

The Chinese builder said it had designed the platform to go for 25 years without requiring docking maintenance.

There were some challenges during construction, around imported materials and difficulties in moving international personnel during COVID-19.

Golar LNG expects to start up the floating LNG (FLNG) Gimi vessel for Tortue Phase 1 in late 2023. The FLNG vessel is 86% complete.

Web Access

Join the global energy conversation

Unlimited web access from just £12.50 per month

Subscribe

energy, Energy Voice | Oil and Gas news

Free weekly Newsletter

A weekly breakdown of forecasts and trends

Enter your contact info to get The Financial Gambits VIP Newsletter for FREE.

We hate spam as much as you, if you dont like it just unsubscribe and we will never bother you again